BUILDER’S HANDOVER PROCESS

BUILDER’S HANDOVER PROCESS

The date of handover from builder to the registered owners association is an important day for new apartment owners and all residents. It has to be taken seriously and detailed due diligence must be done when interacting with the builders during this handover process. Once the formal handover to the Owners Association is completed, the onus is on the association to run the affairs of the society and to ensure its smooth functioning. The association must be prepared for this day for 3+ months leading to this event.

It is recommended that owners collaboratively engage with the builder right from late construction stages that will help them to take-up this responsibility in future. The builders can also reach out to representatives from the owners group to assist in the selection of maintenance agency which prepares them for the handover process.

Based on our experience in interacting with various builders and associations, we have collated a check list that associations can use when in dialogue with the builder on the handover process:

  1. Get approved building plan which includes block-wise and floor-wise details
  2. Collect the Completion Certificate which ensures adherence of the approved plan
  3. No Objection certificates from pollution, fire, water and electricity authorities
  4. Hard copy and soft copy (in CD) of all approved engineering drawings; look for approval seal on the drawings
  5. Registration and parent documents
  6. Drainage, sewage, Fire protection and common area power layout drawings
  7. Car parking layout drawings (with numbering)
  8. Asset Inventory of all movable and immovable equipment purchased; numbered in order (list needs to be exhaustive)
  9. Record of recent service history on key equipment’s like lifts, DG sets, STP and WTP

10.AMC and warranty details; Original bills of equipment purchased (motors, Sewage and Water Treatment Plant, Generators, Gym items like treadmill)

11.Lift license details and next renewal date

12.STP/WTP vendor details, plant layout, operation manual and drawings

13.Receipts of property, electricity and water payments paid

14.Handover of corpus amount to the association

15.Share recent expenses incurred on various maintenance activities and account heads; will assist to budget coming year (staff salaries, purchase of cleaning material, swimming pool maintenance etc)

16.Contract signed with maintenance agency; agreed SLAs

17.Insurance taken for assets and third party lift insurance

18.Audited account statement at the time of handover

  1. Arrange for introductory meeting with important suppliers and vendors
By |March 11th, 2019|Builder’s Handover Process:-|Comments Off on BUILDER’S HANDOVER PROCESS

BUILDER’S HANDOVER PROCESS

BUILDER’S HANDOVER PROCESS

The date of handover from builder to the registered owners association is an important day for new apartment owners and all residents. It has to be taken seriously and detailed due diligence must be done when interacting with the builders during this handover process. Once the formal handover to the Owners Association is completed, the onus is on the association to run the affairs of the society and to ensure its smooth functioning. The association must be prepared for this day for 3+ months leading to this event.
It is recommended that owners collaboratively engage with the builder right from late construction stages that will help them to take-up this responsibility in future. The builders can also reach out to representatives from the owners group to assist in the selection of maintenance agency which prepares them for the handover process.
Based on our experience in interacting with various builders and associations, we have collated a check list that associations can use when in dialogue with the builder on the handover process:
1. Get approved building plan which includes block-wise and floor-wise details
2. Collect the Completion Certificate which ensures adherence of the approved plan
3. No Objection certificates from pollution, fire, water and electricity authorities
4. Hard copy and soft copy (in CD) of all approved engineering drawings; look for approval seal on the drawings
5. Registration and parent documents
6. Drainage, sewage, Fire protection and common area power layout drawings
7. Car parking layout drawings (with numbering)
8. Asset Inventory of all movable and immovable equipment purchased; numbered in order (list needs to be exhaustive)
9. Record of recent service history on key equipment’s like lifts, DG sets, STP and WTP
10.AMC and warranty details; Original bills of equipment purchased (motors, Sewage and Water Treatment Plant, Generators, Gym items like treadmill)
11.Lift license details and next renewal date
12.STP/WTP vendor details, plant layout, operation manual and drawings
13.Receipts of property, electricity and water payments paid
14.Handover of corpus amount to the association
15.Share recent expenses incurred on various maintenance activities and account heads; will assist to budget coming year (staff salaries, purchase of cleaning material, swimming pool maintenance etc)
16.Contract signed with maintenance agency; agreed SLAs
17.Insurance taken for assets and third party lift insurance
18.Audited account statement at the time of handover
19. Arrange for introductory meeting with important suppliers and vendors

By |February 26th, 2019|Builder’s Handover Process|Comments Off on BUILDER’S HANDOVER PROCESS

Builder’s Handover Process

The date of handover from builder to the registered owners association is an important day for new apartment owners and all residents. It has to be taken seriously and detailed due diligence must be done when interacting with the builders during this handover process. Once the formal handover to the Owners Association is completed, the onus is on the association to run the affairs of the society and to ensure its smooth functioning. The association must be prepared for this day for 3+ months leading to this event.
It is recommended that owners collaboratively engage with the builder right from late construction stages that will help them to take-up this responsibility in future. The builders can also reach out to representatives from the owners group to assist in the selection of maintenance agency which prepares them for the handover process.
Based on our experience in interacting with various builders and associations, we have collated a check list that associations can use when in dialogue with the builder on the handover process:
1. Get approved building plan which includes block-wise and floor-wise details
2. Collect the Completion Certificate which ensures adherence of the approved plan
3. No Objection certificates from pollution, fire, water and electricity authorities
4. Hard copy and soft copy (in CD) of all approved engineering drawings; look for approval seal on the drawings
5. Registration and parent documents
6. Drainage, sewage, Fire protection and common area power layout drawings
7. Car parking layout drawings (with numbering)
8. Asset Inventory of all movable and immovable equipment purchased; numbered in order (list needs to be exhaustive)
9. Record of recent service history on key equipment’s like lifts, DG sets, STP and WTP
10.AMC and warranty details; Original bills of equipment purchased (motors, Sewage and Water Treatment Plant, Generators, Gym items like treadmill)
11.Lift license details and next renewal date
12.STP/WTP vendor details, plant layout, operation manual and drawings
13.Receipts of property, electricity and water payments paid
14.Handover of corpus amount to the association
15.Share recent expenses incurred on various maintenance activities and account heads; will assist to budget coming year (staff salaries, purchase of cleaning material, swimming pool maintenance etc)
16.Contract signed with maintenance agency; agreed SLAs
17.Insurance taken for assets and third party lift insurance
18.Audited account statement at the time of handover
19. Arrange for introductory meeting with important suppliers and vendors

By |January 22nd, 2019|Uncategorized|Comments Off on Builder’s Handover Process

Builder’s Handover Process

The date of handover from builder to the registered owners association is an important day for new apartment owners and all residents. It has to be taken seriously and detailed due diligence must be done when interacting with the builders during this handover process. Once the formal handover to the Owners Association is completed, the onus is on the association to run the affairs of the society and to ensure its smooth functioning. The association must be prepared for this day for 3+ months leading to this event.
It is recommended that owners collaboratively engage with the builder right from late construction stages that will help them to take-up this responsibility in future. The builders can also reach out to representatives from the owners group to assist in the selection of maintenance agency which prepares them for the handover process.
Based on our experience in interacting with various builders and associations, we have collated a check list that associations can use when in dialogue with the builder on the handover process:
1. Get approved building plan which includes block-wise and floor-wise details
2. Collect the Completion Certificate which ensures adherence of the approved plan
3. No Objection certificates from pollution, fire, water and electricity authorities
4. Hard copy and soft copy (in CD) of all approved engineering drawings; look for approval seal on the drawings
5. Registration and parent documents
6. Drainage, sewage, Fire protection and common area power layout drawings
7. Car parking layout drawings (with numbering)
8. Asset Inventory of all movable and immovable equipment purchased; numbered in order (list needs to be exhaustive)
9. Record of recent service history on key equipment’s like lifts, DG sets, STP and WTP
10.AMC and warranty details; Original bills of equipment purchased (motors, Sewage and Water Treatment Plant, Generators, Gym items like treadmill)
11.Lift license details and next renewal date
12.STP/WTP vendor details, plant layout, operation manual and drawings
13.Receipts of property, electricity and water payments paid
14.Handover of corpus amount to the association
15.Share recent expenses incurred on various maintenance activities and account heads; will assist to budget coming year (staff salaries, purchase of cleaning material, swimming pool maintenance etc)
16.Contract signed with maintenance agency; agreed SLAs
17.Insurance taken for assets and third party lift insurance
18.Audited account statement at the time of handover
19. Arrange for introductory meeting with important suppliers and vendors

By |January 5th, 2019|Uncategorized|Comments Off on Builder’s Handover Process

Builder’s Handover Process

The date of handover from builder to the registered owners association is an important day for new apartment owners and all residents. It has to be taken seriously and detailed due diligence must be done when interacting with the builders during this handover process. Once the formal handover to the Owners Association is completed, the onus is on the association to run the affairs of the society and to ensure its smooth functioning. The association must be prepared for this day for 3+ months leading to this event.
It is recommended that owners collaboratively engage with the builder right from late construction stages that will help them to take-up this responsibility in future. The builders can also reach out to representatives from the owners group to assist in the selection of maintenance agency which prepares them for the handover process.
Based on our experience in interacting with various builders and associations, we have collated a check list that associations can use when in dialogue with the builder on the handover process:
1. Get approved building plan which includes block-wise and floor-wise details
2. Collect the Completion Certificate which ensures adherence of the approved plan
3. No Objection certificates from pollution, fire, water and electricity authorities
4. Hard copy and soft copy (in CD) of all approved engineering drawings; look for approval seal on the drawings
5. Registration and parent documents
6. Drainage, sewage, Fire protection and common area power layout drawings
7. Car parking layout drawings (with numbering)
8. Asset Inventory of all movable and immovable equipment purchased; numbered in order (list needs to be exhaustive)
9. Record of recent service history on key equipment’s like lifts, DG sets, STP and WTP
10.AMC and warranty details; Original bills of equipment purchased (motors, Sewage and Water Treatment Plant, Generators, Gym items like treadmill)
11.Lift license details and next renewal date
12.STP/WTP vendor details, plant layout, operation manual and drawings
13.Receipts of property, electricity and water payments paid
14.Handover of corpus amount to the association
15.Share recent expenses incurred on various maintenance activities and account heads; will assist to budget coming year (staff salaries, purchase of cleaning material, swimming pool maintenance etc)
16.Contract signed with maintenance agency; agreed SLAs
17.Insurance taken for assets and third party lift insurance
18.Audited account statement at the time of handover
19. Arrange for introductory meeting with important suppliers and vendors

By |December 13th, 2018|Builder’s Handover Process|Comments Off on Builder’s Handover Process

Builder’s Handover Process

The date of handover from builder to the registered owners association is an important day for new apartment owners and all residents. It has to be taken seriously and detailed due diligence must be done when interacting with the builders during this handover process. Once the formal handover to the Owners Association is completed, the onus is on the association to run the affairs of the society and to ensure its smooth functioning. The association must be prepared for this day for 3+ months leading to this event.
It is recommended that owners collaboratively engage with the builder right from late construction stages that will help them to take-up this responsibility in future. The builders can also reach out to representatives from the owners group to assist in the selection of maintenance agency which prepares them for the handover process.
Based on our experience in interacting with various builders and associations, we have collated a check list that associations can use when in dialogue with the builder on the handover process:
1. Get approved building plan which includes block-wise and floor-wise details
2. Collect the Completion Certificate which ensures adherence of the approved plan
3. No Objection certificates from pollution, fire, water and electricity authorities
4. Hard copy and soft copy (in CD) of all approved engineering drawings; look for approval seal on the drawings
5. Registration and parent documents
6. Drainage, sewage, Fire protection and common area power layout drawings
7. Car parking layout drawings (with numbering)
8. Asset Inventory of all movable and immovable equipment purchased; numbered in order (list needs to be exhaustive)
9. Record of recent service history on key equipment’s like lifts, DG sets, STP and WTP
10.AMC and warranty details; Original bills of equipment purchased (motors, Sewage and Water Treatment Plant, Generators, Gym items like treadmill)
11.Lift license details and next renewal date
12.STP/WTP vendor details, plant layout, operation manual and drawings
13.Receipts of property, electricity and water payments paid
14.Handover of corpus amount to the association
15.Share recent expenses incurred on various maintenance activities and account heads; will assist to budget coming year (staff salaries, purchase of cleaning material, swimming pool maintenance etc)
16.Contract signed with maintenance agency; agreed SLAs
17.Insurance taken for assets and third party lift insurance
18.Audited account statement at the time of handover
19. Arrange for introductory meeting with important suppliers and vendors

By |November 16th, 2018|Builder’s Handover Process|Comments Off on Builder’s Handover Process

Builder’s Handover Process

The date of handover from builder to the registered owners association is an important day for new apartment owners and all residents. It has to be taken seriously and detailed due diligence must be done when interacting with the builders during this handover process. Once the formal handover to the Owners Association is completed, the onus is on the association to run the affairs of the society and to ensure its smooth functioning. The association must be prepared for this day for 3+ months leading to this event.
It is recommended that owners collaboratively engage with the builder right from late construction stages that will help them to take-up this responsibility in future. The builders can also reach out to representatives from the owners group to assist in the selection of maintenance agency which prepares them for the handover process.
Based on our experience in interacting with various builders and associations, we have collated a check list that associations can use when in dialogue with the builder on the handover process:
1. Get approved building plan which includes block-wise and floor-wise details
2. Collect the Completion Certificate which ensures adherence of the approved plan
3. No Objection certificates from pollution, fire, water and electricity authorities
4. Hard copy and soft copy (in CD) of all approved engineering drawings; look for approval seal on the drawings
5. Registration and parent documents
6. Drainage, sewage, Fire protection and common area power layout drawings
7. Car parking layout drawings (with numbering)
8. Asset Inventory of all movable and immovable equipment purchased; numbered in order (list needs to be exhaustive)
9. Record of recent service history on key equipment’s like lifts, DG sets, STP and WTP
10.AMC and warranty details; Original bills of equipment purchased (motors, Sewage and Water Treatment Plant, Generators, Gym items like treadmill)
11.Lift license details and next renewal date
12.STP/WTP vendor details, plant layout, operation manual and drawings
13.Receipts of property, electricity and water payments paid
14.Handover of corpus amount to the association
15.Share recent expenses incurred on various maintenance activities and account heads; will assist to budget coming year (staff salaries, purchase of cleaning material, swimming pool maintenance etc)
16.Contract signed with maintenance agency; agreed SLAs
17.Insurance taken for assets and third party lift insurance
18.Audited account statement at the time of handover
19. Arrange for introductory meeting with important suppliers and vendors

FOR MORE DETAILS CALL:
VED LEGAL,
Adv. Gajanan Rahate
Mob: 9763040088
E_mail: [email protected]

By |September 21st, 2018|Uncategorized|Comments Off on Builder’s Handover Process

BUILDER’S HANDOVER PROCESS

The date of handover from builder to the registered owners association is an important day for new apartment owners and all residents. It has to be taken seriously and detailed due diligence must be done when interacting with the builders during this handover process. Once the formal handover to the Owners Association is completed, the onus is on the association to run the affairs of the society and to ensure its smooth functioning. The association must be prepared for this day for 3+ months leading to this event.
It is recommended that owners collaboratively engage with the builder right from late construction stages that will help them to take-up this responsibility in future. The builders can also reach out to representatives from the owners group to assist in the selection of maintenance agency which prepares them for the handover process.
Based on our experience in interacting with various builders and associations, we have collated a check list that associations can use when in dialogue with the builder on the handover process:
1. Get approved building plan which includes block-wise and floor-wise details
2. Collect the Completion Certificate which ensures adherence of the approved plan
3. No Objection certificates from pollution, fire, water and electricity authorities
4. Hard copy and soft copy (in CD) of all approved engineering drawings; look for approval seal on the drawings
5. Registration and parent documents
6. Drainage, sewage, Fire protection and common area power layout drawings
7. Car parking layout drawings (with numbering)
8. Asset Inventory of all movable and immovable equipment purchased; numbered in order (list needs to be exhaustive)
9. Record of recent service history on key equipment’s like lifts, DG sets, STP and WTP
10.AMC and warranty details; Original bills of equipment purchased (motors, Sewage and Water Treatment Plant, Generators, Gym items like treadmill)
11.Lift license details and next renewal date
12.STP/WTP vendor details, plant layout, operation manual and drawings
13.Receipts of property, electricity and water payments paid
14.Handover of corpus amount to the association
15.Share recent expenses incurred on various maintenance activities and account heads; will assist to budget coming year (staff salaries, purchase of cleaning material, swimming pool maintenance etc)
16.Contract signed with maintenance agency; agreed SLAs
17.Insurance taken for assets and third party lift insurance
18.Audited account statement at the time of handover
19. Arrange for introductory meeting with important suppliers and vendors

FOR MORE DETAILS CALL:
VED LEGAL,
Adv. Gajanan Rahate
Mob: 9763040088
E_mail: [email protected]

By |September 17th, 2018|Uncategorized|Comments Off on BUILDER’S HANDOVER PROCESS

BUILDER’S HANDOVER PROCESS

The date of handover from builder to the registered owners association is an important day for new apartment owners and all residents. It has to be taken seriously and detailed due diligence must be done when interacting with the builders during this handover process. Once the formal handover to the Owners Association is completed, the onus is on the association to run the affairs of the society and to ensure its smooth functioning. The association must be prepared for this day for 3+ months leading to this event.
It is recommended that owners collaboratively engage with the builder right from late construction stages that will help them to take-up this responsibility in future. The builders can also reach out to representatives from the owners group to assist in the selection of maintenance agency which prepares them for the handover process.
Based on our experience in interacting with various builders and associations, we have collated a check list that associations can use when in dialogue with the builder on the handover process:
1. Get approved building plan which includes block-wise and floor-wise details
2. Collect the Completion Certificate which ensures adherence of the approved plan
3. No Objection certificates from pollution, fire, water and electricity authorities
4. Hard copy and soft copy (in CD) of all approved engineering drawings; look for approval seal on the drawings
5. Registration and parent documents
6. Drainage, sewage, Fire protection and common area power layout drawings
7. Car parking layout drawings (with numbering)
8. Asset Inventory of all movable and immovable equipment purchased; numbered in order (list needs to be exhaustive)
9. Record of recent service history on key equipment’s like lifts, DG sets, STP and WTP
10.AMC and warranty details; Original bills of equipment purchased (motors, Sewage and Water Treatment Plant, Generators, Gym items like treadmill)
11.Lift license details and next renewal date
12.STP/WTP vendor details, plant layout, operation manual and drawings
13.Receipts of property, electricity and water payments paid
14.Handover of corpus amount to the association
15.Share recent expenses incurred on various maintenance activities and account heads; will assist to budget coming year (staff salaries, purchase of cleaning material, swimming pool maintenance etc)
16.Contract signed with maintenance agency; agreed SLAs
17.Insurance taken for assets and third party lift insurance
18.Audited account statement at the time of handover
19. Arrange for introductory meeting with important suppliers and vendors

FOR MORE DETAILS CALL:
VED LEGAL,
Adv. Gajanan Rahate
Mob: 9763040088
E_mail: [email protected]

By |September 11th, 2018|Uncategorized|Comments Off on BUILDER’S HANDOVER PROCESS

Builder’s Handover Process

SOCIETY FORMATION AND HANDOVER PROCESS BY BUILDER
The Registration process and requirements are governed by Maharashtra State Co-operative Society Act 1960.

To Register Co-op. Housing Society, Minimum 10 member are required.

Less than 10 members Societies are also Registered as per M.S.Govt. Ordinance No. 1094 and 277/14 Dated 10/03/1995. But such member’s flats should be less than 700 Sq.ft. Carpet Area

As per M.S. Govt. Notification dated 24/07/1992 conditions for registrations are liberalized.

60 % of the Promoters are must be ready to form Co-op. Housing Society.
If flats are sold as per the Maharashtra Ownership Flats Act,1963 [MOFA] then it is the duty of the Builder / Developer to form society and hand over the Account + Documents to Provisional Working Committee [PWC] In this case the builder become CP and other flat owners become Promoters for Registration purpose. This society registers under Co-operation.
When the builder is not registering society due to some reasons or not support to registered society then flat purchasers can apply for registration of Co-operative Housing Society under Non Co-operation. In this case one of the flat owners should be elected as CP for Registration purpose. In this case some more time is taken to registered society as registrar is issue notice to builder for Non Co-operation. If no response then ex-party decision are taken for registration of the society. Now all the case of Non Co-operation Registration decisions is given by District Deputy Registrar [DDR] then society is registered
All flat owners should hold meeting and elect Promoter. All power for Registrations, documentation etc. should be given to promoter. The resolution should be passed and must be sign by all flat owners who wish to become member of the Co-operative Housing Society
Appoint Consultant / Legal Advocate for registration and ask him to comply all requirements. All members together also can do work for registration.
For registration of Co-op. Hsg. Society the following documents should be filed to Dy. Registrar / Asst. Registrar of Co-operative Department area concern in order as follow:
• Applications for Name to be reserved for Proposed Society’s
• Form of resolution electing a CP and Promoter and giving them authority for doing certain acts on behalf of the proposed society
• Notice to Builder
• Application form “A”
• Information in Annexure ” A ” ” B ” ” C ”
• Bye-Law of the Society 2 copies
• Details of Accounts Annexure ” D ”
• Bank Balance Certificate in Original
• Namuna 6
• Agreement of 1 Flat
• Advocate Search Report [Title Certificate]
• Society’s Building Plan
• Lay Out Plan
• Sanction Plan from Authority
• Commencement Certificate
• Completion Certificate
• Promoter’s Guarantee in form ” X ” On Rs. 100/- Stamp paper & notarized
• Guarantee in form” Y ” On Rs. 100/- Stamp paper & notarized
• Guarantee in form ” Z ” On Rs. 100/- Stamp paper & notarized
• Latest 7/12 or City Survey Revenue Record of Land [not more than 1 month old]
• Promoters Affidavit On Rs. 100/- Stamp paper & notarized
• Indemnity Bond On Rs. 100/- Stamp paper & notarized
• NA Order
• ULC Order
• Development Agreement and Power of Attorney
• List of Members in the society
• Scheme/Yojana Form
• Registration Fee Challan for Rs.2500
• Builder Non Co-operation form Z On Rs. 100/- Stamp paper & notarized if required 1 copy
On submission of above document the Dy./Asst. Registrar will go through the papers And document. If found OK he will make order for issue of Registration Certificate.
If any deficiencies are found then the applicant will be inform accordingly and documents will be corrected wherever necessary. When all papers are in order, he will issue order for issue of Registration Certificate.
Registration Certificate is issued with covering letter and Officer’s name is mentioned who will attend First General Meeting. Normally the Officer concern is not attending meeting. In absence, all members has to hold meeting and has to elect Provisional Working Committee [PWC] whose working period will be ONE Year.
After electing PWC the member of PWC has to submitted the M-20 bond on Rs. 100/- stamp paper with the sign of Officer’s whose name is in Covering latter to Dy./Asst. Registrar. All Rule and Regulations, resolution and minutes which is written in AGM Register must be sign by Officer’s name is mentioned in covering letter it is the most important step.[Many society forget this which create problem latter] After First Annual General Meeting PWC is replaced with new Working Committee [WC] whose working period will be FIVE Year. The new WC election can conduct before PWC time over with proper election process. WC also has to submitted the M-20 bond on Rs. 100/- stamp paper with the sign of election officer to Dy./Asst. Registrar.
When application for Name reservation of Society has given, the Dy./Asst. Registrar give instruction to Open Bank Account in Dist. Central Co-op. Bank The Account has to opened in the name of CP And deposit all money of Share Capital Contribution [per member Share Money is Rs. 50*10 = Rs. 500 i.e. 10 share of 50 rupees each] and Member ship Fees of Rs. 100/- i.e. Per member you have to deposit Rs. 600/- in bank and obtain Bank Balance Certificate and submitted it to Dy./Asst. Registrar. After First Annual General Body Meeting the Bank Account has to transfer in the name of Society. For bank Account operation Chairman sign must and either Secretary and Treasurer. Expenditure has to be made as per provision of Bye-Laws. Bank and Cash Transaction [Collection and Payment are handled by Treasure when Billing Clerk or Accountant are not been kept.

FOR MORE DETAILS CALL:
VED LEGAL,
Adv. Gajanan Rahate
Mob: 9763040088
E_mail: [email protected]

By |September 4th, 2018|Builder’s Handover Process|Comments Off on Builder’s Handover Process